The Singapore-registered vessel TERAS BETHEL is docked at the Jutao Shipyard in Penglai Port.
On January 21, 2014, the Singapore-registered vessel TERASBETHEL docked at the Jutao Shipyard in Penglai. As the project agent, our company assisted the vessel in handling port entry and exit procedures, coordinating the ballast and supply materials with the dock's captain, and other tasks. With the joint efforts of all parties, the heavy cargo was successfully loaded and secured, departing the port on January 28. In this project agency, our company received praise from heavy industry enterprises, shipowners, and various port authorities.
04
2014
/
03
COSL shipowner cargo loading at Qingdao Qianwan Port
On January 23, 2014, COSL imported 2*40FL to Qingdao Qianwan Port. Due to the cargo being oversized, it was necessary to arrange for unpacking at the dock and loading onto low chassis trucks for transportation to Yantai. However, at that time, it was close to the Spring Festival, and the supplier also needed to unload on-site. Therefore, our company arranged for relevant personnel to go to Qingdao Qianwan Port to handle the unpacking and loading of the goods before February 13, 2014, and safely transported the goods to Yantai Raifushi Shipyard the next day.
26
02
Notice regarding the issues related to the 2014 Level 2 Construction Engineer Professional Qualification Examination
Transportation of large cargo
Loading Port: Penglai Jutao Ocean Heavy Industry Co., Ltd. Dock POL: PJOE Unloading Port: Ulsan, South Korea, Hyundai Heavy Industries Dock POD: HHIport, Ulsan Korea Cargo Information: Mooring Support Structure, 19m*22m*8m, 260T CargoInfo: Mooring Support Structure, 19m*22m*8m, 260T Loading Period: 2013.11.8 Laycan: 2013.11.8
25
2013
11
HYUNDAI DUBAI successfully loaded and departed the port.
On November 4, 2013, the HYUNDAIDUBAI began loading. This voyage needed to load cargo for the third voyage of the Hyundai Icebreaker TIHAMA project and the fourth voyage of the HANJU project. Since these two batches of cargo were the last for their respective projects and the shipping schedule was very tight, both the owner and company leaders attached great importance to the loading work of this voyage. Our field personnel also made meticulous plans in advance with the dock instructors and the ship's captain to strive to complete the loading work with quality and quantity in the shortest time possible. Ultimately, with the active cooperation of all parties involved.
14
Longkou Ship Agency
Since the establishment of our Longkou branch, our colleagues have been dedicated to providing the highest quality service to our customers, receiving unanimous praise from customers at Longkou Port. Our company has established a long-term cooperative relationship with the fertilizer cargo owner, Qingdao Mingtai Trading Co., Ltd. Since June 2013, we have provided long-term ship agency services for foreign fertilizer vessels, accumulating dozens of voyages. This includes vessels such as Badge No. 2, Golden Eagle, and Changda 368, with services receiving unanimous praise from cargo owners and shipowners.
28
10
The second voyage of the modern ice wheel TIHAMA project for cargo collection and loading has been successfully completed.
On September 17, 2013, the second voyage of the TIHAMA project began gathering cargo, which ended on October 12. The loading work for this voyage on the HANDE vessel started on October 13. With the reasonable arrangement of cargo loading and lifting processes by our on-site personnel, the ship's captain, and the port authorities, the loading work was completed on October 14, and the ship successfully departed from the port. Among them, a single module weighing 170 tons is one of the heaviest single weights of our exported goods at Yantai Port.
24
The third voyage of cargo collection and loading for the Yantai to Dashan HDO#9 project has been successfully completed.
On September 22, 2013, the third voyage of the HDO#9 project began gathering cargo, which ended on September 29. Due to the continuous delay of the CHANGYING vessel's schedule, loading work started on October 7 after the National Day holiday. With the full cooperation of our on-site staff, dock personnel, the shipping company, and the bundling staff, the loading work was completed on October 9, and the vessel departed smoothly. Thus, the HDO#9 project from Yantai to Dashan has been fully completed, with a total loading volume of 1,448 pieces, 4,300.655 tons, and 17,172.55 cubic meters.